Corruption: Rural Electrification & Renewable Energy Corporation Purchases Overpriced, Fake Electricity Poles

There’s a corruption scandal at the newly rebranded parastatal.

Rural Electrification Authority (REA) changed its name to Rural Electrification and Renewable Energy Corporation (REREC) following the enactment of the Energy Act 2019.

REREC’s mandate is to spearhead Kenya’s green energy drive, in addition to implementing rural electrification projects.

Hi Nyakundi,

This tender has been designed for a company called Ecopole, which President Uhuru Kenyatta went to visit in Limuru last year. A cabinet paper was passed by PS Energy to approve the use of composite and KPLC, as well as Rural Electrification and Renewable Energy Corporation (Rerec), were forced to procure 60,000 poles at 60,000 but with bulk order to be reduced to Sh55,000 per pole. This is thrice the price of concrete poles.

Kenya Power & Lighting Company Plc (KPLC) Bernard Ngugi MD refused to procure for the last 4 months and thus tender was channelled through Rerec, by CEO and Chairman both from Mount Kenya.

Technology has not been proven anywhere and is 3 times the price of concrete poles.

The tender document specifications are as Ecopoles brochure, and the standard is for poles being dropped from a forklift at 3 metres high, which is a farce considering that there is no such test in the world. The product doesn’t conform to any International Standard for Composites and has never been used anywhere in the world, though it is marketed as Norwegian and United Nations (UN) etc.

There are local manufacturers who have set up a plant for real composite products but they have been sidelined by the tender document which has covered sizes, strengths and designs of Ecopole.

Ecopole is a rudimentary technology never proven anywhere with false claims of UN goals etc and no certification of such approvals. Furthermore, it states that it is fully recyclable but it is foam filled which isn’t recyclable anywhere in the world. Basically, a waterpipe stuffed with bamboo twigs and filled with foam.

This is high-level impunity calling for delivery of 15,000 poles in 7 months, why the rush for the delivery, does REREC install 15,000 poles in 7 months.

This corruption must be stopped.

Documents


There's no story that cannot be told. We cover the stories that others don't want to be told, we bring you all the news you need. If you have tips, exposes or any story you need to be told bluntly and all queries write to us [email protected] also find us on Telegram

Related posts

GRAND TWEEF: GrandMulla Counsel AHMEDNASIR And Senator MURKOMEN Goes On A Public Word Rampage

nairobi-exposed

PHOTOS: New Female Gospel Artist Turns Heads With Her DAZZLING Looks

nairobi-exposed

JUA CALI Schools MIKE SONKO

nairobi-exposed

Top Rankings Of KCPE 2013 Results

nairobi-exposed

Some Kenyans Are Extremely RICH Check Out The Sh 240 Million CAR That Arrived At JKIA This Morning

nairobi-exposed

SELFIE Game Madness Takes Over The Internet By Storm,Hilarious Photos Gallery

nairobi-exposed

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More